20250 Hwy 45 N
Weston, MO 64098
United States
Latitude: 39.4472
Longitude: -94.98
Year Opened: 1980
Water Source: Missouri River
Cost (in millions): 2000
The second unit will cost approximately $2 billion (a 2008 estimate).
Installation of one opposed-wall-fired, dry-bottom, boiler (8100 mmBtu/hr), subbituminous coal with No. 2 oil backup and associated equipment, including cooling tower : Identical project also proposed for Great Plains Weston Bend (MO). Will only build one or the other.
very near construction the proposed one
EJN Coal Spreadsheet 2006/2007
EIA 2008
Sierra Club: Stopping the Coal Rush
Coal Swarm
EIA 2012 Form 860
EIA 2014 Form 860