3002 US Hwy 421 North
Wilmington, NC 28401
United States
Latitude: 34.28202
Longitude: -77.95906
Year Opened: 1984
Water Source: Well
5/2013: deconstruction of stack & flues.
1/2013: gave up on plans to refurbish.
6/2012: pursuing contract w/Covanta to refurbish.
4/2011: closed while county decides whether to refurbish it.
3/2011: to make the facility operational would probably take upwards of $20m. Currently, the incinerator is operating only 1 of 3 boilers.
"The system has a 500 ton-per-day capacity that includes two original 100 ton-per-day boilers along with a 300 ton-per-day boiler added in 1991 pursuant to a $27 million bond for expansion. The plant processes approximately 140,000 tons of feedstock per year. When operational, the system produces steam to turn two electrical generators and has a 10.5 megawatt capacity"
EIA 2008